Adding EV chargers, a heat pump or new machinery puts extra demand on a building’s electrical supply, and not every supply has the spare capacity. A load assessment tells you whether yours can cope before you commit to the equipment.
This guide covers what a commercial load assessment should include, how the checks change with the equipment, what you should get after the survey, and what happens if there isn’t enough capacity.
Ask a competent electrical contractor to assess the proposed load before you finalise equipment purchases or promise a commissioning date. The assessment should consider the existing supply, the condition and suitability of the installation, and how current and proposed equipment will operate together.
The result should tell you which way to go: install as designed, gather more evidence, phase or manage the new demand, or look at an upgrade. If the network connection needs to change, the local Distribution Network Operator (DNO) has to assess what is available.
An electrician’s survey is not network approval. Equally, available network capacity does not prove that the cables and distribution equipment inside your premises are suitable.
A load assessment helps identify how the installation is used and what the proposed change may require. It does not itself grant a larger network supply or approve an installation design. The contractor should explain which conclusions are supported by the assessment and which need further design, equipment information or discussion with the network operator.
Start with the electricity account, any connection agreement, electrical drawings and reports from previous work. Where a Maximum Import Capacity is agreed, it sets a connection limit and should not be confused with the rating printed on an individual switch.
Each network operator publishes its own guidance. Northern Powergrid’s guidance on adding to your supply covers businesses installing machinery or expanding, and it is the operator for much of Yorkshire. National Grid Electricity Distribution’s load-change guidance, which covers the Midlands, South West and Wales, explains that agreed import capacity is measured in kilovolt-amperes (kVA), and that an increase may require connection or network work. Your contractor should identify the relevant network operator for your address rather than assuming the same process applies everywhere.
A recent Electrical Installation Condition Report (EICR) can provide useful condition information. It does not automatically answer whether a particular new load can be added. Tell the contractor you need an assessment for the proposed project, not simply a copy of the last report.
Say when demand peaks, for example at shift changes or during busy production runs, and whether heating is seasonal. Mention anything that runs outside opening hours.
Existing demand data can help, but its limitations matter. A quiet week or an annual energy total may not show the peak conditions the design needs to accommodate. Ask whether monitoring is needed, how the monitoring period will be chosen and how seasonal or unusual operating conditions will be addressed.
You do not need to install monitoring equipment yourself. Agree the access and safe working arrangements with the contractor.
The assessment should look beyond the incoming supply. Ask whether the proposed route, distribution equipment and circuits are suitable, and what further inspection or design work is needed.
In a three-phase installation, the distribution of demand between phases can also matter. A single total for the building does not tell you everything about the part of the installation that will feed the new equipment.
Ask for any inaccessible areas or unverified assumptions to be identified. An early survey may establish feasibility without providing the final circuit design, installation specification or full price.
EV chargers: charging needs matter as well as charger ratings
Tell the contractor how many vehicles need charging, how long they stay and when they need to leave. Overnight fleet charging is a different requirement from a short visitor stop.
Ask whether the chargers could share an agreed allowance, and how that would change charging times. Load management reduces how much is drawn at once, but it does not create extra power, and the vehicles still need to get the charge they came for.
Your EV charger installer should confirm which DNO application or notification applies before connection. A rule that works for a single domestic charger may not apply to a larger commercial scheme.
Heat pumps: what to tell the contractor
Give the contractor the manufacturer’s electrical requirements rather than just the advertised heating output, and include any associated equipment and backup or supplementary electric heating.
Talk through winter operation and whether the heating will run at the same time as the building’s other busy periods. Choosing the heat pump and assessing the electrics need to inform each other, so neither should rest on a guessed allowance.
Machinery: starting and running requirements
Ask the equipment supplier for the electrical specification, the starting requirements and the expected duty cycle. Tell the contractor which machines may run together and whether production plans are likely to change.
Motors and welders raise questions that go beyond simply adding up their rated power. National Grid Electricity Distribution’s guidance specifically flags equipment that may affect network voltage. Your electrical contractor and equipment supplier should say whether more technical information or a conversation with the network operator is needed.
Agree the deliverables before booking. A useful written assessment should make the next decision easier, rather than leave you with an unexplained capacity figure.
What the written assessment should give you
| Deliverable | What it should show |
|---|---|
| Measured or assessed demand | The evidence reviewed and any monitoring undertaken or still required. |
| Assumptions | The proposed equipment and operating assumptions used in the assessment. |
| Constraints | The constraints identified in the supply or internal installation. |
| Options | The options available and the practical limits of each. |
| Decisions needing further approval | Input still needed from the DNO, supplier, landlord or a specialist, plus the next design, quotation and approval steps and what is excluded. |
Ask the contractor to distinguish confirmed findings from provisional estimates. If the equipment specification changes, expect the assessment to need updating as well.
An upgrade is one possible outcome, but not the only question to explore. The contractor may consider different equipment, controlled demand or a phased installation, provided the proposed arrangement is suitable and meets the business need.
A business planning several chargers, for example, might weigh managed charging against a larger supply upgrade. What matters is whether vehicles get the charge they need in the time available, not how many sockets can be fitted.
If an upgrade is necessary, separate work on the network connection from work within the premises. SSEN’s capacity-change guidance, from another network operator, illustrates why the network operator, electrical contractor and energy supplier may each have a role. Confirm the responsibilities for your own connection and obtain project-specific dates and quotations.
Don’t count solar panels or batteries as guaranteed spare capacity. Generation varies, storage has limits on how it operates, and any proposed control arrangement needs assessing. Tell the contractor what generation or storage you have or plan, and what happens when it isn’t available.
Do not remove electrical covers or attempt to inspect the incoming fuse to fill gaps in the paperwork. Leave technical checks and any work on the installation to competent people.
It can provide useful account and usage information, but energy consumed over time is not the same as peak demand. The contractor also needs to assess the installation and proposed operating conditions.
No. Physical space does not mean the supply, board, cabling or protective arrangements are suitable for the proposed load. A competent designer must assess the addition.
Not necessarily. The equipment specification and assessed demand determine what is required. A three-phase supply is not, by itself, proof of enough capacity.
That depends on the available records, access, need for monitoring and whether network or other third-party work is required. Ask for a programme specific to the project rather than relying on a general lead time.
No. An EICR assesses the condition of the existing installation within an agreed scope. A load assessment addresses the proposed demand and the suitability of the arrangements to support it. A project may need both.
Related reading
Calder Electrical has been providing electrical services to residential, commercial and industrial properties for over 40 years, and we are specialists in all aspects of electrical installations, maintenance and inspection and testing.
All our work is fully insured, and we work to the standards set by the NICEIC. Our team provides electrical maintenance, installation servicing and a call-out service for unplanned issues.
Request a load and capacity survey
If you would like help planning an addition to your premises, contact us to request a load and capacity survey. Bring the equipment details and your intended timescale so we can discuss the next steps.
Or would like us to provide a survey and quote then please contact us and we will be happy to help.
Call us on 0800 612 3001